Sunday, September 19, 2010

Commissioning Data Center

Last week we walked around the new data center for the management company to perform pre-functional and functional testing (depending on the equipment). The UPS still couldn't be tested because there were still issues with a transfer switch. We looked at the 4 CRAC units, one of which was still hooked up to the vacuum to remove moisture before being re-charged with refrigerant. The two larger CRACs had to have their refrigerant removed, be cut in half to get in the elevator, and then re-assembled. There were a couple of problems with the wiring of one of these, the result of a wiring harness being re-installed improperly. Both of the large units needed to have insulation added since it was removed when it was cut (photo to the right). There was also a very small domestic water copper pipe used for humidification that should be insulated and secured to the frame so that it didn't vibrate against the frame and eventually wear through (photo on the left - the larger diameter pipe was secured with a vibration dapening clamp). One of the large CRAC units was moving 16% less air than it should and the motor was going to be re-shived to fix.

Another of th
e issues we looked for were un-sealed penetrations in the floor and ceiling since both were being used as a plenum for supply (floor) and return (celing) air. The floor was sealed pretty good with only a couple of penetrations that were missed (photo on the left), but the ceiling had lots of unsealed penetrations (photo on the right). Kevin Sheehan (on the ladder) and Kevin Bright (in the floor) are using a flashlight to look for these issues in the photos below.





















Another issue we identified during this trip was the chilled water pressure gauges, which were supposed to be 6" diameter and instead were 4" diameter. Obviously this isn't a huge deal, but they were pretty clearly called for in the spec and we've asked the contractor to replace.



Thursday, March 18, 2010

Francis Lab Commissioning


On Friday, March 5th, Kevin Bright, Kevin Sheehan, Philip Kreycik, and I met with representatives from the electrician, controls contractor, balancer, and construction manager as part of the commissioning process for the Francis Lab in the Harvard Biolabs building. We checked every occupancy sensor in the space, including those that control the overhead lights and thermostats as well as those that control the task lighting at all of the lab benches. Many of the overhead occupancy sensors were located too close to air diffuser vents and would never shut off, so we had to re-set the sensitivity (in most cases electing to switch them to infrared only rather than using the ultrasonic / infrared dual technology). We also put each fan coil unit into heating and cooling modes and checked schedules and worked with Siemens to fix anything we found such as opportunities for simultaneous heating and cooling or non-responsive thermostats. While there, we compared what was installed to the drawings to see if the as-built drawings needed to be updated. We found a couple of concrete penetrations without sleeves, but determined this was outside the scope of work for this project. We also found a hole in a compressed air line that would need to be repaired. Finally, we checked the face velocity for the fume hoods, making sure that they stayed at 100 fpm at all sash heights. Unfortunately, some peculiarities with the building's HVAC system didn't allow us to run the face velocity any lower. The first fume hood we tested wasn't programmed properly and wasn't responding to the sash height. Kevin Bright continued the functional testing process for the remaining building systems after the rest of the Harvard Office for Sustainability team left and we've since shared our list of issues with the project manager. This is one of multiple visits to the site as construction winds down, which is part of the functional testing component of commissioning. At OFS, we always try to conduct full ASHRAE Guideline 0 commissioning and include plumbing systems in addition to energy systems and include user training in addition to occupant training. We've found the process to be extremely beneficial and cost effective for the interior fit-out projects that we're targeting.

Friday, August 28, 2009

Owner's Project Requirements Charette

On Wednesday we held a goal setting meeting for the Sherman Fairchild project (a laboratory building full gut renovation). Representatives from the Architect, MEP Engineer, Project Management, Operations and Maintenance, Occupants, Office for Sustainability (both the green building services and the occupant engagement groups), Engineering and Utilities, IT, and EH&S were present to decide what constituted a "successful" project. Establishing goals and measures of success up front is important to getting everybody on the same page and should help quicken the design process and minimize change orders as all stakeholders have had a chance to provide their feedback.









Project goals were collected in the areas of "Project Performance", "Environmental Performance", "Human Health and Comfort", "Operations and Maintenance", and "Training and Education". OFS staff lead the meeting using the Nominal Group Technique, which collects a list of ideas from all stakeholders, gives attendees time to ask clarifying questions, and then ranks the goals to identify the most important. We'll take the results and compile a ranked set of project goals and the Owner's Project Requirements (OPR). The design team will respond to these documents in each of their design submittals and the commissioning authority will use OPR during the commissioning process. The agenda for the four hour meeting is attached here.

Wednesday, August 26, 2009

Kovac Lab Commissioning


Jesse Foote, Kevin Sheehan, and I visited the Kovac Lab on Thursday to do some of the functional testing / witness testing. The lighting controls weren't ready yet, but we confirmed the air balancing for supply and exhaust, went over the heat pump and condensate pump checklist, verified fire dampers and access panels, checked as-built drawings, looked for pipe insulation and labels, and reviewed the thermostat settings. The project looked really good and the gentleman from Comfort Air Solutions out of Framingham was really helpful. We found a large wall penetration above the ACT for cables that should be filled in (the lab calls for negative pressure and deck-to-deck partitions). We also found one fire damper that was covered up and made inaccessible as well as some un-labeled piping. The biggest concern was a lack of control dampers on the two outside air ducts. We drilled holes for a traverse in one and found the outside air to be over 37% higher than called for by the design engineer, which would result in a lot of extra heating and cooling energy. We didn't bother testing the second intake because of the lack of a control damper made making changes impossible at this time. A couple of issues were outside of the scope of work of the current project team, like no air being exhausted from the restrooms (despite supply air being delivered and an exhaust air grill) and existing air diffusers in one room directing supply air directly at the exterior wall and windows (we suggested rotating the diffuser 180 degrees). Our final recommendation was to review the thermostat schedule with the occupants and include occupant training as part of building turnover, as it seemed like the current occupied hours setting of 6:00 AM to 7:00 PM for weekdays and 6:00 AM to 6:00 PM for weekends might be unnecessarily long. We'll return soon to confirm the lighting controls.

Friday, April 3, 2009

Fume Hood Ventilation


The Jacobsen Lab in Harvard University's Mallinckrodt Building uses Mott variable volume fume hoods to help save energy by reducing the volume of air being exhausted (and as a result reducing the fresh air brought into the space that needs to be heated or cooled) as the hood sash is closed. The hoods are saving additional energy by having air movement with 80 feet per minute face velocity entering the hood, reduced from the typical 100 fpm or higher in most hoods (the hood was tested and demonstrated safe containment at 60 fpm). To ensure occupant safety, each hood has a digital display indicating the face velocity, with an alarm sounding if it were to go too low and a purge button that allows the occupant to increase volume to 300% of normal if there is a spill. Occupants are educated about the hoods' operations and then provided with large digital displays at the entrance to the lab that indicate total volume of air being exhausted in cubic feet per minute. Lab users know what the volume should be if all hoods are closed and can quickly assess whether a hood was left open and is unnecessarily wasting energy (as Philip Kreycik is doing in the pictures above and below). The newly renovated Jacobsen lab is pursuing a Gold rating from the US Green Building Council's Commercial Interior rating system and has integrated a number of sustainable design elements into the project.

Sunday, March 8, 2009

Hip Hop Archive Cx


A few weeks ago the Harvard Office for Sustainability and Harvard Facilities Maintenance Operations commissioned the newly renovated Hip Hop Archive in Cambridge, MA. The project is part of the W.E.B. Du Bois Institute for African and African American Research. These pictures show Kevin Sheehan (FMO) and Kevin Bright (OFS) looking at one of the heat pumps and the associated condensate pump (pouring in a cup of water to make sure it starts up correctly). The project is finishing up the LEED for Commercial Interiors certification process and will be submitted soon. The picture on the bottom should include an outside air duct brought into the heat pump (as shown on the "as-builts"), but it isn't there. We added it to our report.