Tuesday, August 4, 2009

Holyoke 4th Floor Commissioning


This morning we conducted functional testing as part of our commissioning of the Holyoke Center 4th Floor fit-out. During the electrical portion of the commissioning, we confirmed all occupancy sensors were working correctly and set to the proper timing (the first project we've looked at with all occupancy sensors working correctly before commissioning). However, we noticed that the light fixtures were not dimming up and down based on the presence of daylight as they were supposed to. It turns out they needed to be set up with the photosensor tool before they'll dim, but this had not been done. We were able to work with the lighting installer and have them set the minimum (nearly off) and maximum (set to provide just over 50 foot candles at the work surfaces rather than fully on) levels for each fixture. We also made sure operating the daylight responsive dimming feature was added to the operator training planned for the next day.


No comments: